Change request calculator

Load the approved scope from the scope calculator or enter it manually, mark the work progress and describe the changes. The calculator shows affected modules, extra hours, money and weeks, risks and a before/after comparison — and builds a change order without altering the original agreement.

Free, no sign-up

First set the approved scope: load a scope-snapshot file from the scope calculator or enter the modules manually.

From a scope-snapshot file

The file the Scope and cost calculator exports with “Approve the scope”. The scope is locked and becomes read-only.

Enter manually

Modules from the contract or estimate: hours and cost as low and high bounds. If there is a reserve, enter it separately — totals include it.

Used to derive team capacity; you can leave 0 and enter capacity later.

The document is stored only in this browser. InterLAB rules v1.0 (2026-10-13): rework surcharge +20% (in progress) and +40% (done), credit only for the unfinished share, re-planning when a change exceeds 20%.

How the calculator works

  1. Approved scope

    A scope-snapshot file from the Scope and cost calculator, or modules entered manually with hours and cost. Once locked, the scope is read-only, and who approved it and when is always shown.

  2. Work progress

    Each module is not started, in progress (with a percentage) or done. The status drives the rework surcharge and the credit for removals.

  3. Requests CR-001, CR-002…

    Each request has a title, a reason, who asked and when, and a list of changes: add a module, change a module (± hours or ± %), remove a module.

  4. Impact

    Δ hours, money and weeks, a before/after table, affected and dependent modules, risks under published rules and the calculation behind every number.

  5. Approval

    Draft → submitted → approved or rejected, with the decision maker and date. An approved request is pinned as a version and cannot be edited; a rejected one stays in the log.

Calculation rules

Add a module

Rule
Hours (low–high) × rate. The rate is entered or the average rate of the approved scope: Σ cost ÷ Σ hours; the derivation is shown

Change a module: ± hours or ± %

Rule
A percentage applies to each hour bound of the module. Cost uses the module's own rate (its cost ÷ its hours)

Rework surcharge

Rule
On hours added to a module in progress +20%, done +40%: some finished work is redone

Reduce a module

Rule
Only the unfinished share is credited: reduction × (1 − done share); a done module credits 0

Remove a module

Rule
Credit = module hours and cost × unfinished share. The finished part is not credited and stays in the scope, marked

Reserve

Rule
The approved scope's reserve applies to the change — so the scope snapshot stays consistent

Schedule

Rule
Δ weeks = Δ hours with reserve ÷ team capacity. Capacity is entered or “hours ÷ weeks” of the approved scope
Calculation rules v1.0 (2026-10-13)

Risk rules

Risks are hints with an explanation, not a verdict: the client and the contractor decide.

CR-RISK-DONE

Level
high
When it fires
Changing or removing a done module

CR-RISK-INPROG

Level
medium
When it fires
Changing or removing a module in progress

CR-RISK-BIG

Level
high
When it fires
The change exceeds 20% of the approved cost (or hours if there is no cost) → re-planning recommended

CR-RISK-CUM

Level
medium
When it fires
Together with earlier approved changes the scope has grown by more than 20%

CR-RISK-LATE

Level
medium
When it fires
More than 60% of the work is done (by module hours)

CR-RISK-DEP-REMOVE

Level
high
When it fires
A module that other modules depend on is removed

CR-RISK-RIPPLE

Level
medium
When it fires
The changed module has dependents (transitively) — review them

CR-RISK-NEW-DEP

Level
medium
When it fires
A new module depends on a module that is not in the current scope

CR-RISK-DEADLINE

Level
high
When it fires
Planned end + shifts of all approved CRs and this CR is after the deadline
Risk rules

Limitations

  • The change estimate inherits the approved scope's assumptions: if the original estimate is off, so is this one.
  • A new module uses the scope's average rate by default; if the work needs a different role (for example design only), enter the rate manually.
  • The schedule shift uses total team capacity and ignores that a change may land on one overloaded role.
  • Approval is a note as stated by the user — not an electronic signature and not a contract amendment.

Privacy

  • Everything is calculated in your browser: the calculator itself does not send the scope, requests or text to a server, and they never appear in the page address.
  • The document and versions are stored only in this browser (localStorage); “Clear all” deletes them. Share via JSON and Markdown/PDF files.
  • Analytics receives only the fact of a submission, decision or export and categories (risk level, number of changes, format) — no amounts or text.
  • The result reaches us only if you send a request yourself and keep the “Attach the result” box ticked — the form shows exactly what will be sent.

Related tools

All tools · 40
Tell us about your task — we'll review your request and get back to you

Is the project scope changing mid-flight?

An InterLAB technical consultation helps review the changes, rebuild the plan and agree on new boundaries. The first short conversation is free; the cost is set after a brief.

  • The first short conversation is free — we choose the format
  • NDA — yours or ours
  • Pricing after a brief and an agreed scope

Please do not send passwords, access keys or source code through this form — we will agree a safe way to share access separately.

By clicking the button you agree to the processing of your personal data.